Low Pitch Roof Installation

low pitched roof

At a low pitch, several sections of the roof system are functioning at the limit of their capabilities, suggesting an increased possibility of collapse during harsh weather conditions. This potential vulnerability emphasizes the need for careful design and material selection.

Rather than relying on ordinary roofing construction, which is good for steeper roofs, it is important to specify and build the roof to safeguard susceptible regions such as eaves, valleys, abutments, roof window surrounds, and other similar connections. Addressing these vulnerable areas can significantly enhance the roof’s overall durability.

Manufacturers thoroughly test roof tiles to ensure they are suitable for their intended purpose. There will be conditions, though, when snow or rain makes its way through the tile joints; notably when the tiles may not be seated as tightly as typical as they pass over, for example, flashings.

Modern vapour permeable underlays do not compress in the manner that the old bituminous felts did, therefore they cannot seal around the batten nails nearly so effectively. It is thus vital to build the full roof system so that it remains watertight. Ensuring a watertight roof system is critical for preventing long-term damage.

Low-pitched roofs are commonly installed on building additions, where they may have to cope with water shedding from a bigger roof above, often as a point load via a downpipe shoe, or in concentrated loads from valleys, dormer side abutments, etc. So cautious design is vital, with such point loads avoided if feasible. Avoiding these point loads can greatly reduce the risk of water damage.

This article covers how to design and install an appropriate system for usage at low roof slopes. Proper installation techniques are key to ensuring the longevity of low-pitched roofs.

SCOPE

Read this guide in combination with the installation guide, specification, and other relevant guidelines for the particular tile. This approach ensures that all aspects of the installation are thoroughly understood.

Install the roof and other Sandtoft components in line with the manufacturer’s instructions, BS 5534, and BS 5250. Following these standards helps maintain the quality and longevity of the roof system. Carry out all site work using regular standards of excellent workmanship and in conformity with the criteria of BS 8000-6: the British Standard Code of Practice for workmanship on building sites.

ROOF CONSTRUCTION

Ideally, the roof should be boarded, but it is understood that this is not standard practice in many areas of the UK, hence this advice assumes that the roof is not boarded. This recommendation balances ideal practices with common construction methods. It presupposes that the rafters are spaced at no more than 600mm centres and the tile battens are attached to the rafters using counterbattens.

ROOF SYSTEMS

For comprehensive information on installing dry fix and ventilation systems, refer to the installation instructions for the particular system. Proper ventilation is crucial for the roof’s performance and lifespan.

UNDERLAY

Lay Sandtoft VPM Super underlay horizontally over the rafters with a 10mm drape between each rafter. This installation method helps to ensure proper coverage and water runoff. Allow a minimum 150mm horizontal lap between courses and minimum 100mm vertical laps.

If required, raise the horizontal lap to match with a tile batten. Adjustments like this can improve the overall fit and finish of the roof. Ensure there are no rips, tears, or holes generally in the underlay.

Repair any that do arise with Sandtoft Multi-tape or discard and replace as necessary. Prompt repairs will help maintain the integrity of the underlay. Seal all laps with Sandtoft double-sided tape . Seal all roof joints with Sandtoft Multi tape. Sealing joints effectively is critical to preventing moisture infiltration.

Lay Sandtoft butyl nail tape over the underlay, corresponding with the rafters and any other fixing points. This ensures proper alignment and effective sealing of the underlay.

Remove backing tape, then install counterbattens over the nail tape and rafters, fastening at maximum 300mm centres. Proper fastening will help maintain the integrity of the roof structure.

Counterbattens prevent water pooling behind the tile battens and protect the nail tape from foot activity during construction. They should be 50mm broad and may be any thickness from 10mm. Using the correct dimensions is essential for optimal performance.

Fix tile battens over the counterbattens, nailing using 65 x 3.35mm smooth round steel nails. Ensure the nails are driven securely to prevent any movement of the battens.

Joints should be square cut; butted centrally on counterbattens and must not occur more than once in any set of four battens on any one rafter. (Refer to the Sandtoft installation instructions for battens). This will help maintain a uniform and stable surface for the tiles.

Seal all underlay laps and counterbattens fixed to protect nail tape. Nail tape should be applied over rafters and other anchoring points to ensure a watertight seal.

USING NAIL TAPE WITHOUT COUNTERBATTENS

If placing nail tape without counterbattens, then it is necessary to secure small strips immediately beneath the battens and other fixes. This alternative method requires careful attention to detail.

Firstly, draw out the placements of the battens using a chalk line. Position the nail tape at the chalk lines, directly over the rafters and other fixing points. Then position the battens to the chalk lines and nail through the nail tape into the rafters. Following these steps precisely ensures that the battens are properly aligned and secured.

VENTILATED EAVES

Set the fascia height, including over fascia ventilator if required, to guarantee a fall to the underlay support tray. If this means the eaves course tiles cannot be laid to the same angle as the tiles above, then it will be necessary to install a ventilation strip or tilt batten over the underlay support tray. Adjustments like these are crucial for maintaining proper ventilation and water runoff.

A batten must be notched to facilitate the free flow of water from underlay to gutter. Ensuring proper drainage will help prevent water damage and extend the life of the roof.

Fix spacer trays continually to guarantee the free passage of air between the underlay and insulation at the wall plate. Adequate ventilation is key to preventing condensation and related issues.

If required, depending upon the level of insulation, fix additional spacer trays (sold separately). The correct number of spacer trays is essential for maintaining airflow and insulation effectiveness.

Lay underlay support trays over the fascia, overlapping each by 100mm. Seal the laps between underlay support trays with Sandtoft MultiFix glue. Overlapping and sealing the trays properly will help ensure a watertight system.

Lap the underlay over the underlay support trays by at least 150mm. Use MultiFix adhesive or double-sided tape to secure the underlay to the underlay support trays. Proper lapping and sealing will prevent water ingress at the eaves.

Position the first tile batten such that tiles overhang the gutter by 45 to 55mm. Nail all eaves course tiles and clip if necessary by the fastening standard. This positioning is crucial for effective water drainage and roof longevity.

Small pieces of nail tape should be placed across rafters and other anchoring points to ensure a consistent seal. Wood with weep holes or vents should be used to set tiles to the proper tilt, with the underlay support tray installed to ensure water flows correctly to the eaves.

ROOF WINDOW

Install the roof window surround in line with its manufacturer’s instructions. Proper installation will ensure that the window is securely and effectively integrated into the roof system.

Turn the general underlay up against and apply it to the window surround using Sandtoft Multi-tape. Seal the underlay at each window corner using Sandtoft Multi-tape. These steps are crucial for maintaining a watertight seal around the window.

Where available, place a supplementary underlay skirt around the window. This additional layer provides extra protection against water ingress.

Alternatively, construct a skirt from Sandtoft VPM Super underlay. Make a slit in the general underlay above the window to make a lap over the skirt and seal with Sandtoft Multi-tape. Seal the skirt over the tiling battens and general underlay with Sandtoft Multi-tape. Ensuring a secure seal between the underlay and the window will prevent leaks.

Install the roof window flashings in line with its manufacturer’s specifications. Following the manufacturer’s guidelines ensures the flashings are properly installed and effective.

Install the tiling over the window flashings. Where necessary at the side flashings, gently remove tile nibs to minimize ‘kicking’ over the flashings. Use stainless steel screws, instead of nails, to fix the tiles over the window flashings. This method will provide a more secure and durable attachment for the tiles.

Top Roofing Contractor in Singapore

Looking to install your roof with long-lasting and attractive tiles? Visit waterproofing.com.sg for professional roofing services that combine style with durability. Get in touch with us today to learn more!

Related Articles:
Roofing Services
Types of Roof Repairs for a Home
Roof Leakage